Indian staff yet to resume work on key power transmission projects linked to Rooppur Nuclear Plant
UNB
Publish: 22 Sep 2024, 01:08 PM
Dhaka,
Sept 22 (UNB)-Senior officials from Indian companies involved in critical power
transmission projects in Bangladesh, which are essential for evacuating
electricity from the Rooppur Nuclear Power Plant (RNPP), have yet to return to
their jobs, raising concerns about the progress of these projects.
"Few staff from KEC
International Limited and Transrail Lighting Limited (TTL) have returned, but
none from Larsen and Toubro Limited (L and T) or other companies
have come back," a top official from Power Grid Bangladesh PLC told UNB.
The official clarified that the returning staff are mostly locally recruited
temporary workers and mid-level officials from KEC, with no senior officials
back on site yet.
However, another senior
Power Grid Bangladesh official indicated that Indian staff from L and T are
expected to rejoin the projects from September 24. "We are waiting to see
them resume their work," the official said.
The return of Indian
personnel has been delayed since all staff from Indian companies left
Bangladesh following the fall of the Awami League government on August 5, in
the wake of a mass uprising. As a result, the transmission projects involving
Indian contractors have come to a standstill.
Currently, Indian
companies are engaged in 17 transmission projects across Bangladesh, with L and
T, Transrail, and KEC being the primary contractors. Some of these projects are
crucial for connecting the Rooppur NPP, scheduled to begin operation in
December this year, to the national grid.
"The sudden
departure of Indian contractor staff has created uncertainty around these
critical projects," said the Power Grid Bangladesh official.
Larsen and
Toubro, one of the key contractors, has been awarded major contracts to
build transmission infrastructure necessary for evacuating electricity from
Bangladesh's first nuclear power plant in Rooppur, Pabna. The company is
responsible for installing 400kV and 230kV transmission lines, which are
critical components of the grid synchronization and testing process for the
RNPP's first unit, now scheduled for completion in early 2025.
The transmission
project, estimated to cost Tk 10,981 crore, is being financed primarily by Exim
Bank (Tk 8,219 crore), with contributions from the Bangladesh government (Tk
1,527 crore) and Power Grid Bangladesh (Tk 1,235 crore).
According to the Power
Grid Bangladesh PLC, the transmission project includes five major packages-the
464km long 400kV transmission lines, including a 13km river crossing; 205km
long 230kV transmission lines, including 7km river crossing; 400kV five Bay
extensions; 230kV four bay extensions; and qualitative upgradation of
Bangladesh power system for frequency control and frequency drop protection,
protection system, emergency control system and other associated tasks.
END/UNB/SH/KW